Madam Speaker, the situation with Tanoso Irrigation Scheme is very similar to the one I just answered with regard to Akomadan.
The Tanoso Irrigation Project was selected as one of the nine (9) out of 22 public irrigation schemes for rehabilitation under the Ministry of Food and Agriculture. The rehabilitation was funded by the World Bank and Government of Ghana and the beneficiaries are the small-scale farmers in Tanoso and its surrounding communi-ties.
It was tendered for rehabilitation under Agricultural Subsector Investment Programme (AgSSIP) in January, 2005.
The tenders were evaluated and a contractor was selected.
A contract was signed on 2nd August, 2005, between the Ministry of Food and Agriculture and Messrs SAT Engineering Limited.
The site was handed over to the contractor on 24 th September, 2005. The contractor mobilized equipment and personnel and work started on 10th October, 2005.
The rehabil i tat ion works were programmed for completion within a year, precisely by December 31, 2006. Madam Speaker, we are in 2009.
The civil works comprising the construction of pump house, farmers meeting hall, roads, stores (for farm produce, fertilizer, chemicals, et cetera) and on farm irrigation works which comprised replacing old asbestos cement pipes with new PVC pipes and construction of hydrant chambers, were completed on December 31, 2007.
The community requested extension of the scope of works to include the expansion of the delivery to the expanded area. These extra works were completed by December 31, 2008.
The completed works have not been handed over to the farmers because the installations of pumps and sprinklers which were under separate contracts were outstanding.
The contract for pumps was awarded, as in the case of Akomadan to the same Indian company, KIRLOSKA in November, 2006. And the contract for on farm equipment, that is, the laterals and the sprinklers, was awarded to the same JAIN IRRIGATION SYSTEMS LIMITED in December, 2006.
Madam Speaker, delays in establishing Letters of Credit (LC) have accounted for the delay in this project. The LCs were finally established in March, 2007 and May, 2007 respectively.
However, the pumps have arrived in