There are eight (8) ongoing projects under the Eastern Corridor projects.
The Eastern Corridor road which has both gravel and bituminous surfaced sections in poor conditions, is located across the following districts: South Dayi, Afadjato South, Hohoe, Nkwanta South and Nkwanta North, all in the Volta Region and Yendi, Nanumba North and Gushiegu Districts all in the Northern Region.
Upgrading of Asikuma Junction - Have Road (km 0.0 -45.0)
The project which is located in the South Dayi District was awarded on 29th September, 2011. It commenced on 5th December, 2011 for completion by 5th December, 2013. The completion date was revised to 5th March, 2017, as a result of the employer's delay in paying for the work done.
Current physical progress is 52 per cent. The contractor is at the site working and has requested for additional 12 months extension of completion time. This is being reviewed by the employer.
The project is financed from the Consolidated Fund. The contractor has placed asphaltic concrete binder course on the 28.0 km length of the road.
Reconstruction of Have - Hohoe road (km
0.0 - 20.0)
The project is located in the Afadjato South District. The 20 km road project was awarded on 23 rd March, 2016. It commenced on 12 th April, 2016 for completion by 11th October, 2017, a period of eighteen (18) calendar months.
The project is being financed by Ghana Cocoa Board (COCOBOD) and is currently estimated at 58 per cent physical completion.
COCOBOD in a letter dated 30th May, 2017, directed the supervising consultant, Ghana Highway Authority (GHA), to inform all contractors working on COCOBOD funded road projects to suspend works with immediate effect.
This is to enable COCOBOD undertake a general review and rationalisation of the projects. Therefore, the contractor has accordingly suspended works. Work done includes 14.8 km of primer seal and 4.8 km of seal.
Reconstruction of Have - Hohoe road (km
20.0 - 51.3)
The project is located in Afadjato South and Hohoe Municipal Assemblies. It was awarded on 4th March, 2016. It commenced on 12 th April, 2016 for completion in thirty-six (36) calendar months; that is by 11th April, 2019. The road length is 31.3km.
Current physical progress is estimated at 40 per cent. The project is funded by COCOBOD. COCOBOD in a letter dated 30th May, 2017, directed the supervising consultant (GHA) to inform all contractors working on COCOBOD funded road projects to suspend works with immediate effect.
This is to enable COCOBOD undertake a general review and rationalisation of the scope of the projects. The contractor has accordingly suspended works.
A total length of about 15.0 km of the road has been primer sealed.
Reconstruction of Hohoe - Jasikan Road ( km 2.0 - 32.0)
The project is located in the Hohoe, Biakoye and Jasikan Districts. It was awarded on 21st August, 2015.The project commenced on 7th December, 2015 for completion by 6th December, 2017.
There has been an extension of time of twelve (12) months, which has brought the extended contractual completion date to 5th December, 2018. This was as a result of additional works covered by a Variation Order (VO).
Current physical progress is 37 per cent. The project is being funded by COCOBOD. The road on completion will have a double bituminous surface dressing.
The employer (COCOBOD) has directed the supervising consultant (GHA) to inform all contractors working on COCOBOD funded road projects to suspend works with immediate effect.
The contractor has accordingly suspended works.
A total length of 4.9 km of the road has been primer sealed.
Rehabilitation of Dodo Pepesu - Nkwanta Road (km 0.0 - 46.4)
The road is 46.4 km long and is located in Nkwanta South District of the Volta Region. It was awarded on 11th June, 2012.The project commenced on 5 th
September, 2012, for completion by 4th
March, 2014, a period of eighteen (18) calendar months.
This original completion date was extended to 4th November, 2014 and then to 4thOctober, 2015 due to excessive rainfall within the project corridor and additional works.
The Project is 100 per cent complete with a double bituminous surface dressing wearing course. The road was financed from European Development Fund.
Upgrading of Nkwanta - Oti Damanko Road (km 0.0 - 50.3)
The road is located within the Nkwanta South and Nkwanta North Districts of the Volta Region. This road section is 50.3 km long, unpaved (graveled surfaced) and in poor condition.
The project was awarded on 29 th
September, 2011.The works commenced on 22nd November, 2011 for completion by 21st
November 2013, a period of twenty-four (24) calendar months.
The contractual completion date has been extended to 5th March, 2017, but has since expired. It is currently at 32 per cent physical completion. The project is financed from the Consolidated Fund (GoG).
The project has suffered cash flow challenges due to the employer's delays in paying for work done. The contractor is on site working and has requested for an extension of completion time of thirty- six (36) months which is being reviewed by the Employer.
The road on completion will have an asphaltic concrete surface. To date 11.0 km of base course has been placed.
Reconstruction of Nkwanta-Oti Damanko road (km 50.3 - 62.3)
The project covers a section of the Nkwanta - Oti Damanko road. It is 12.0km gravel surfaced road which is in poor condition and is located in the Nkwanta North District of the Volta Region. It starts from a community called Sibi.
The project is financed from the Ghana Road Fund. On completion, the road will have an Asphaltic Concrete Surface.
The contract for the Sibi - Oti Damanko section (12.0 km) was awarded on 21st June, 2016. The project commenced on 2nd