Mr Speaker, Anobil,
Dwirigom, Foleso, Ashyiam,
Dankwawora, Agyedom, Asasetere and
Kojo Yaw communities formed part of
the Ministry's electrification project earmarked for execution by M/S Weldy
Lamont & Associates Inc. in the Amenfi
Central Constituency of the Western
Region. The project originally targeted to
connect 1,200 communities in all three
(3) beneficiary regions, namely; Central,
Oral Answers to Questions
Western and Brong Ahafo Regions, to the
national electricity grid. During the
implementation of the project, however,
more communities were added for
connection to the Grid which increased
the targeted communities to 2,251.
The electrification project was
completed in May 2022, having connected a
total of 2,127 communities to the
National Grid. Unfortunately, installation
works in some 124 communities,
including the mentioned ones, could not
be completed as the project fund could
not cover them. M/S Weldy Lamont &
Associates Inc. has submitted the project
completion report, and a reconciliation
exercise is being done to determine the
scope of works outstanding in the
remaining communities.
Following the take-over of the
outstanding works, the Ministry will re-
package them for completion as part of
the on-going SHEP. Suponso, Nyame
Dome and Nso Nyame Ye communities,
however, do not form part of any of the
Ministry's ongoing electrification programmes. The communities have,
therefore, been noted for consideration in
future electrification programmes.